Footing should be on native undisturbed soil. If the soil is not strong enough, you have to excavate further until the capable soil. Fill the hole with lean mix before the concrete footing. You need to tell the supplier that the lean mix will be for footing (may ask 1 MPa?). Otherwise the supplier will give you less kpa likely (less than 400kpa) although labeled with 400kPa. They assumes that you will cut/chip it later.
Can you fill the hole with same concrete if you do not care for the cost? This mean to have footing 250 mm depth in some area and 1000 mm in other area for instance. To be conservative, ask structural engineer.
By the way, you work for yourself?
Can you fill the hole with same concrete if you do not care for the cost? This mean to have footing 250 mm depth in some area and 1000 mm in other area for instance. To be conservative, ask structural engineer.